A contractor employed 30 men to do a piece of work in 38 days. After 25 days , he employed 5 men more and the work was finished one day earlier. How many days he would have been behind, if he had not employed additional men?
একটি অপশন বেছে নিন
একটি অপশন বেছে নিন
আগের প্রশ্ন
A person borrows Tk. 5000 for 2 years at 4% p.a. simple interest . He immediately lends to...
পরের প্রশ্ন
A garrison of 500 men had provisions for 27 days . After 3 days a reinforcement of 300 men...
A garrison of 500 men had provisions for 27 days . After 3 days a reinforcement of 300 men arrived . For how m...
উত্তর ও ব্যাখ্যা দেখুন MathIf 8 men can reap 80 hectares in 24 days , then how many hectares can 36 men reap in 30 days ?
উত্তর ও ব্যাখ্যা দেখুন MathA man completes
উত্তর ও ব্যাখ্যা দেখুন MathIf the radius of a circle is increased by 6% , then the area is increased by :
উত্তর ও ব্যাখ্যা দেখুন MathIf the height of a triangle is decreased by 40% and its base is increased by 40% , what will be the effect on...
উত্তর ও ব্যাখ্যা দেখুন MathA tank is 25 m long , 12 m wide and 6 m deep. The cost of plastering its walls and bottom at 75 paise per sq.m...
উত্তর ও ব্যাখ্যা দেখুনএটি Math বিষয়ের একটি গুরুত্বপূর্ণ MCQ প্রশ্ন, যা বিসিএস, ব্যাংক জব, প্রাইমারি শিক্ষক নিয়োগ ও অন্যান্য সরকারি-বেসরকারি চাকরির পরীক্ষায় বারবার আসার সম্ভাবনা থাকে। প্রশ্নটির সঠিক উত্তর A) 1।
JobGenius BD™-তে আপনি Math বিষয়ের আরও অনেক MCQ ব্যাখ্যাসহ প্র্যাকটিস করতে পারবেন, দুর্বল জায়গা চিহ্নিত করে নিয়মিত প্রস্তুতি নিতে পারবেন।
সঠিক উত্তর: A) 1।
প্রশ্নটি Math বিষয়ের অন্তর্ভুক্ত।
জব প্রিপারেশন পেজ থেকে বিষয়ভিত্তিক সব MCQ প্র্যাকটিস করতে পারবেন।
এখানে ক্লিক করে ভুলটি জানান, আমরা যাচাই করে সংশোধন করব।