Mr. Jamal employed 50 workers to finish a work within 30 days. After 20 days he found out that only 50% work had been completed. How many additional workers would be need to finish the task in scheduled time?
একটি অপশন বেছে নিন
একটি অপশন বেছে নিন
আগের প্রশ্ন
Topu's income is Tk.2,000 more than that of Jamal. Their total salary is Tk.x. What is Jam...
পরের প্রশ্ন
The ratio of boys and girls in a class is 4:5. If 10% of the boys and 20%of the girls fail...
The ratio of boys and girls in a class is 4:5. If 10% of the boys and 20%of the girls failed In an examination...
উত্তর ও ব্যাখ্যা দেখুন MathIn a store,shirts are sold for 25% less than the tag price. If a shirt costs Tk.480, what would be the tag pri...
উত্তর ও ব্যাখ্যা দেখুন MathArif is 4 times as old as Bobby,in 6 years, Bobby will be twice as old as Sara. Four years from now Arif will...
উত্তর ও ব্যাখ্যা দেখুন MathIf the average (arithmetic mean) of x and y is 60 and the average(arithmetic mean)of y and z is 80,what is the...
উত্তর ও ব্যাখ্যা দেখুন MathFive boys or 9 girls can do a piece of work in 19 days.In how many days can 3 boys and 6 girls do this work?
উত্তর ও ব্যাখ্যা দেখুন MathBy selling a TV for Tk.29,500 instead of Tk.30,000,the profit decreases by 10%. What is the cost of the TV in...
উত্তর ও ব্যাখ্যা দেখুনএটি Math বিষয়ের একটি গুরুত্বপূর্ণ MCQ প্রশ্ন, যা বিসিএস, ব্যাংক জব, প্রাইমারি শিক্ষক নিয়োগ ও অন্যান্য সরকারি-বেসরকারি চাকরির পরীক্ষায় বারবার আসার সম্ভাবনা থাকে। প্রশ্নটির সঠিক উত্তর A) 50।
JobGenius BD™-তে আপনি Math বিষয়ের আরও অনেক MCQ ব্যাখ্যাসহ প্র্যাকটিস করতে পারবেন, দুর্বল জায়গা চিহ্নিত করে নিয়মিত প্রস্তুতি নিতে পারবেন।
সঠিক উত্তর: A) 50।
প্রশ্নটি Math বিষয়ের অন্তর্ভুক্ত।
জব প্রিপারেশন পেজ থেকে বিষয়ভিত্তিক সব MCQ প্র্যাকটিস করতে পারবেন।
এখানে ক্লিক করে ভুলটি জানান, আমরা যাচাই করে সংশোধন করব।