Rashid can do a piece of work in 8 days, which Tipu can finish in 12 days. If they work at it on alternate days with Rashid beginning, in how many days, the work will be finished?
একটি অপশন বেছে নিন
একটি অপশন বেছে নিন
আগের প্রশ্ন
If the radius of a circle is increased by 1% then the area of that circle increases by wha...
পরের প্রশ্ন
Two equal glasses are respectively one-third and one-fourth full of milk. they are then fi...
Two equal glasses are respectively one-third and one-fourth full of milk. they are then filled up with water a...
উত্তর ও ব্যাখ্যা দেখুন MathThe ratio between two numbers is 3:4 and their least common multiple is 180. What is the first number?
উত্তর ও ব্যাখ্যা দেখুন MathThe distance between two stations, Dhaka and Chittagong is 450 km. A train starts at 5 pm from Dhaka and moves...
উত্তর ও ব্যাখ্যা দেখুন MathThe simple interest on a sum of money will be Tk. 600 after 10 years. If the principal is trebled after 5 year...
উত্তর ও ব্যাখ্যা দেখুন MathWhich one of the following is the next number in the series : 7, 7, 14, 42, 168-----?
উত্তর ও ব্যাখ্যা দেখুন Math12 year old Manick is three times as old as his brother Rahul. How old will Manick be when he is twice as old...
উত্তর ও ব্যাখ্যা দেখুনএটি Math বিষয়ের একটি গুরুত্বপূর্ণ MCQ প্রশ্ন, যা বিসিএস, ব্যাংক জব, প্রাইমারি শিক্ষক নিয়োগ ও অন্যান্য সরকারি-বেসরকারি চাকরির পরীক্ষায় বারবার আসার সম্ভাবনা থাকে। প্রশ্নটির সঠিক উত্তর B) 19/2 days।
JobGenius BD™-তে আপনি Math বিষয়ের আরও অনেক MCQ ব্যাখ্যাসহ প্র্যাকটিস করতে পারবেন, দুর্বল জায়গা চিহ্নিত করে নিয়মিত প্রস্তুতি নিতে পারবেন।
সঠিক উত্তর: B) 19/2 days।
প্রশ্নটি Math বিষয়ের অন্তর্ভুক্ত।
জব প্রিপারেশন পেজ থেকে বিষয়ভিত্তিক সব MCQ প্র্যাকটিস করতে পারবেন।
এখানে ক্লিক করে ভুলটি জানান, আমরা যাচাই করে সংশোধন করব।